Connect a motor in star or delta? How to read the nameplate, connect the motor correctly and reduce the starting current with star-delta starting.
AI This article was created with the help of AI.
Table of contents
- Voltage ratio and power in star or delta
- Reading the nameplate and connecting the motor correctly
- Star-delta starting: current reduction and changeover point
- Star-delta switch and contactor circuit
- Setting motor protection correctly and avoiding errors
- Limits of star-delta starting and modern alternatives
- Frequently asked questions
- Sources
Voltage ratio and power in star or delta
Whether a three-phase asynchronous motor is connected in star or delta is determined by the nameplate and the available mains voltage. A standard three-phase mains in Europe provides a line-to-line voltage of 400 V at 50 Hz between two line conductors. On a motor’s nameplate, the lower voltage figure states the rated voltage of a single winding phase.
The difference between star (Y) and delta (Δ) connection is based on the linkage factor √3 (approx. 1.73). In delta connection, the full line voltage of 400 V is applied to each winding phase. In star connection, the three winding phases are joined at a common star point; each phase receives only the phase voltage U_phase = U_mains / √3, i.e. about 230 V at 400 V.
Because phase current and torque fall with the phase voltage, the power consumption in star connection is one third of the power in delta connection, and so is the starting torque[1]. In practice, the starting torque is in fact only about 25 to 28 % of the torque at full voltage[2]. For the design, this means: a motor with 230VΔ/400VY must be operated permanently in star on a 400 V mains so as not to overload the phase windings. If a motor is to run in delta on a 400 V mains or start via star-delta starting, a motor with 400VΔ/690VY is required[1].
| Operating parameter | Delta connection (Δ) | Star connection (Y) | Ratio (Y / Δ) |
|---|---|---|---|
| Voltage per winding phase | 400 V | 230 V | 1 / √3 (approx. 58 %) |
| Phase current | 100 % rated phase current | 58 % rated phase current | 1 / √3 |
| Mains line current | 100 % rated current | 33.3 % rated current | 1 / 3 |
| Available torque | 100 % rated torque | 33.3 % rated torque | 1 / 3 |
| Power | 100 % rated power | 33.3 % rated power | 1 / 3 |
Reading the nameplate and connecting the motor correctly
The nameplate of a switchable motor shows two voltages and two currents, for example 230/400 V and the associated rated current for each. The lower voltage belongs to the delta connection, the higher one to the star connection; the higher current belongs to the delta connection. The stated power is the shaft power, i.e. the mechanical output power[3]. This is how to match nameplate and mains:
| Nameplate | Mains 3 × 230 V | Mains 3 × 400 V | Star-delta starting on a 400 V mains |
|---|---|---|---|
| 230/400 V (Δ/Y) | Delta | Star | not possible |
| 400/690 V (Δ/Y) | not suitable, winding receives too little voltage | Delta | possible |
In the terminal box, the winding starts are designated U1, V1, W1 and the winding ends U2, V2, W2 in accordance with IEC 60034-8[1]. The line conductors L1, L2, L3 are connected to U1, V1, W1. For star-delta starting, all six winding connections must be brought out individually; the links in the terminal box are removed and the contactors take over the connection[1]. For the star connection, the star link connects U2, V2 and W2 to form the star point. For the delta connection, three links connect U1 to W2, V1 to U2 and W1 to V2. You change the direction of rotation by swapping two line conductors; for permanently alternating directions of rotation, a reversing switch takes over.
The same rule applies to the frequency converter, except that the output voltage of the converter counts instead of the mains voltage: if it supplies 3 × 400 V, a 230/400 V motor is connected in star; a single-phase-fed converter with a 3 × 230 V output requires the delta connection for the same motor.
Star-delta starting: current reduction and changeover point
When switched on directly, a squirrel-cage motor draws a starting current of 6 to 8 times the rated current[2]. Under the German Technical Connection Conditions, motor starts must not cause disturbing voltage changes in the grid[4]. In the public grid, this is considered fulfilled if an occasionally starting three-phase motor has a starting apparent power below 5.2 kVA or its starting current does not exceed 60 A. At 400 V and eight times the starting current, this corresponds to a shaft power of 4 kW; motors above 4 kW with 400/690 V can be started via star-delta starting[3]. Energy suppliers permit this starting circuit up to 11 kW, in some cases even higher[1].
A worked example: a motor with a rated current I_N of 30 A and a starting current factor I_A / I_N = 6 draws around 180 A when started direct-on-line in delta. With a star-delta contactor combination, the starting current falls to one third: 180 A / 3 = 60 A, i.e. exactly the 60 A value; for this motor size, check with your grid operator whether the start is permissible. How to determine the rated current from the power is shown in our article Converting kW to amps. At the same time, the starting torque falls to one third, which the driven machine must allow.
The decisive factor is the moment of changeover from star to delta:
- Changeover point: Changeover takes place only when the motor has run up to 75 to 80 % of its rated speed. If the changeover is too early, a strong current surge occurs and the overcurrent protection devices can trip despite star-delta starting[1].
- Changeover pause: Between the star contactor dropping out and the delta contactor picking up, at least 50 ms is recommended so that the arc of the star contactor is extinguished[1].
- Changeover current peak: If the mains and the residual field of the rotor are unfavourably aligned at reconnection, the peak can, depending on how the line conductors are assigned to the windings, reach up to twice the current of direct-on-line starting in delta[1]. It is reduced by matching the changeover pause and the connection of the line conductors to each other; some terminal connections deviate from the three usual delta links for this purpose[1].
- Mechanical shock: A simulation with a 5 ms switching delay produced negative torque peaks of almost 15 times the rated torque and a peak current of about 25 times the RMS value of the rated current[4]. A typical damage pattern of such a negative torque surge is a feather key damaged on its rear side[4]; all mechanical transmission elements of the drive train are subjected to stress.
Star-delta switch and contactor circuit
Star-delta starting is available as a manually operated star-delta switch and as a contactor circuit. With the manual switch, the interlock between the star and delta positions is mechanical[1]. The automatic contactor circuit works with three contactors and a timing relay:
- Start: The line contactor picks up and holds itself via its own auxiliary contact; at the same time, the star contactor picks up, the motor runs up in star and the timing relay starts[5].
- Changeover: After the set time, typically 5 to 10 seconds depending on the run-up behaviour, the star contactor drops out and the delta contactor picks up. The changeover pauses in the control circuit are typically 30 to 100 ms[5].
- Interlock: An NC contact of the star contactor prevents the delta contactor from picking up at the same time, and vice versa[6]. In the main circuit, a mechanical interlock of the two contactors is added[5], because if both pick up at the same time, a short circuit occurs.
Without a timing relay, the changeover is manual: once the motor has reached its rated speed, the operator presses a push-button for the delta stage[6]. For alternating directions of rotation, the starter can be extended with a reversing contactor to form a star-delta reversing circuit[1]. For sizing purposes, the line and delta contactors carry the phase current in continuous operation, i.e. around 0.58 × I_N. The star contactor carries only the current reduced to one third in star during the starting phase and may be smaller.
Setting motor protection correctly and avoiding errors
Thermal overload relays or motor protection circuit breakers protect against thermal overload and phase failure. Their setting depends on their position in the circuit diagram. If the overcurrent relay is located after the line contactor in series with the winding, it is set to the phase current 0.58 × I_N. If it is in the supply line upstream of the contactor combination, the tripping current is set to the rated motor current; in this case, however, the motor is protected against overload only in the delta connection, i.e. in rated operation[6].
| Installation location of the protective device | Current flowing | Setting on the trip unit | Practical assessment |
|---|---|---|---|
| In the winding branch (phase) | Phase current (I_phase) | I_N / √3 = 0.58 × I_N | Standard solution: also protects in the star starting phase. |
| In the mains supply line | Mains line current (I_mains) | I_N (full rated current) | Larger protective device; overload protection only in delta operation. |
The most serious error in practice is connecting a 230/400 V motor in delta to a 400 V mains. Each winding then receives 400 V instead of 230 V, i.e. √3 times its rated voltage. Current and heating rise far above the rated values, and the winding insulation is damaged if the motor protection does not trip in time. Therefore, check the nameplate and the links in the terminal box before every connection.
Limits of star-delta starting and modern alternatives
Because the starting torque is only one third, star-delta starting is only suitable for light starting conditions, such as unloaded flywheel masses, fans or pumps. If the motor has to deliver more than one third of its rated power in star, it can be overloaded[1]. If the driven machine already requires a high load torque at breakaway, the motor does not reach the changeover speed in star. The switching frequency is also limited: there is no general figure for permissible starts per hour, because the rotor heats up with high slip during every run-up; the data for the respective motor are authoritative. If frequent switching causes disturbances in the public grid, further measures are necessary for motors with more than 30 A starting current[3].
- Soft starters (soft start units): They change voltage and torque continuously and avoid transient processes, whereas star-delta starting is only suitable for no-load or light-load starting[4]. The current and torque jump at changeover is eliminated.
- Frequency converters: Unlike star-delta switching, they make reduced current consumption possible while still providing a high starting torque[1]. In addition, they control the speed during operation.
We compare which of the two solutions suits your machine in our article Soft starter vs. frequency converter. It is important to look at the entire drive train: starting method, gearbox design and brake must match. As a supplier for the complete drive train, we at ATEK Drive Solutions design motor, gearbox and brake to fit precisely from a single source. You will find an overview of our IEC standard motors in our product range, and we will be happy to advise you personally on your specific application via our contact page.
Frequently asked questions
When does a motor have to be connected in star and when in delta?
That depends on the nameplate and the mains voltage. The lower voltage on the nameplate applies to delta, the higher one to star. On a 400 V mains, a 230/400 V motor is connected in star and a 400/690 V motor in delta. On a 230 V three-phase mains or converter output, a 230/400 V motor runs in delta.
What does 230/400 V on the motor nameplate mean?
Each winding phase is designed for 230 V. The motor may therefore be operated on 3 × 230 V in delta and on 3 × 400 V in star. It is not suitable for star-delta starting on a 400 V mains; this requires a motor with 400/690 V.
Why is star-delta starting used?
It reduces the starting current, which reaches 6 to 8 times the rated current with direct-on-line starting, to one third. This protects the grid against voltage dips. Because in star each winding receives only the voltage reduced by √3, the starting torque also falls to one third.
From what power rating is star-delta starting required?
In the public grid, direct-on-line starting of an occasionally starting motor is unproblematic up to 5.2 kVA starting apparent power or up to 60 A starting current; at 400 V and eight times the starting current, this corresponds to a shaft power of about 4 kW. Above this, a current-reduced start is necessary; the requirements of your grid operator are authoritative.
What happens if you change over too early with star-delta starting?
The motor should have reached 75 to 80 % of its rated speed. If the changeover is too early, a strong current surge occurs that can trip the overcurrent protection devices. Depending on the assignment of the line conductors, the changeover current peak can reach up to twice the direct-on-line starting current.
What value must the motor protection relay be set to?
That depends on the installation location. In the winding phase after the line contactor, the relay carries the phase current and is set to 0.58 × rated current. In the mains supply line, it carries the full line current and is set to the rated current; it then protects the motor only in delta operation.
Must a motor on a frequency converter be connected in star or delta?
The output voltage of the converter is what counts. With a 3 × 400 V output, a 230/400 V motor is connected in star; with a single-phase-fed converter with a 3 × 230 V output, in delta.
Is a frequency converter better than a star-delta circuit?
Technically yes, if the machine starts under load or the speed is to be controlled: the converter enables reduced current with high starting torque and no changeover shock. For fans, pumps and other light starts at fixed speed, star-delta starting remains a simple and cost-effective solution.
Sources
- Wikipedia (DE): Stern-Dreieck-Anlaufschaltung (star-delta starting circuit)
- elektropraktiker.de (DE): Starting three-phase asynchronous motors
- KEM Konstruktion (DE): Motor start – what to consider when using three-phase asynchronous motors
- elektropraktiker.de (DE): Star-delta starting or soft start for squirrel-cage motors
- mechatronik-automatisierung.com (DE): Star-delta circuit
- elektrotechnik-hilfe.at (DE): Star-delta contactor circuit